@classick Several work periods on the TransCon, including some activity on the Sibley bridge and some track work a bit farther east, near Camden. If the work occurs between Bucklin, MO, and Kansas City, it is possible to send a few trains via the old BN Brookfield Sub. Due to a lack of crews available on that line, however, not all traffic can be rerouted that way. Only the highest-priority trains thus are detoured. All others are simply delayed until work is close to being done.
Several work periods on the TransCon, including some activity on the Sibley bridge and some track work a bit farther east, near Camden. If the work occurs between Bucklin, MO, and Kansas City, it is possible to send a few trains via the old BN Brookfield Sub. Due to a lack of crews available on that line, however, not all traffic can be rerouted that way. Only the highest-priority trains thus are detoured. All others are simply delayed until work is close to being done.